Legislation #: 931276 Introduction Date: 11/4/1993
Type: Ordinance Effective Date: 12/2/1993
Sponsor: None
Title: Authorizing a contract in the amount of $55,048.90 with Total Electric Construction Co. for constructing a traffic signal modification for Prospect at 59th Street; estimating revenue and appropriating $48,179.00 to the project account; and authorizing expenditure of $60,554.00 in funding therefor.

Legislation History
DateMinutesDescription
11/3/1993

Prepare to Introduce

11/4/1993

Referred Operations And Aviation

11/17/1993

Do Pass

11/18/1993

Add to Consent Docket

11/22/1993

Passed


View Attachments
FileTypeSizeDescription
No attachment(s) found

Printer Friendly Version

 

ORDINANCE NO. 931276

 

Authorizing a contract in the amount of $55,048.90 with Total Electric Construction Co. for constructing a traffic signal modification for Prospect at 59th Street; estimating revenue and appropriating $48,179.00 to the project account; and authorizing expenditure of $60,554.00 in funding therefor.

 

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

 

Section 1. That the work of constructing a traffic signal modification for Prospect at 59th Street, consisting of mast arms, traffic controller, pull boxes, conduit and other necessary appurtenances, in Council District 5, Kansas City, Jackson County, Missouri, Project No. 4032, Federal Project No. STPG-3462(402), is hereby provided for and authorized.

 

Section 2. That the work shall be done in accordance with the plans, specifications and the contract therefore between Kansas City, Missouri, through its Director of Public Works, and Total Electric Construction Co., a foreign corporation, in the amount of $55,048.90, which contract is on file in the office of the Director of Public Works and is incorporated herein by reference.

 

Section 3. That the revenue in the following account of the Capital Improvements Fund is hereby estimated in the following amount:

 

309-089-7882 STP Grant - 59th and Prospect Signals $48,179.00

 

Section 4. That the sum of $48,179.00 is hereby appropriated from the Unappropriated Fund Balance of the Capital Improvements Fund, to the following account in the Capital Improvements Fund:

 

309-089-7705T Traffic Signal Interconnection $48,179.00

 

Section 5. That the Director of Public Works is hereby authorized to expend the sum of $60,554.00 from funds heretofore appropriated to Account No. 309-089-7705T as and for consideration in the aforesaid contract and for contingencies and engineering associated therewith.

 

_____________________________________________

 

I hereby certify that there is a balance, otherwise unencumbered, to the credit of the appropriation to which the foregoing expenditure is to be charged, and a cash balance, otherwise unencumbered, in the treasury, to the credit of the fund from which payment is to be made, each sufficient to meet the obligation hereby incurred.

 

 

___________________________________

Director of Finance

 

 

Approved as to form and legality:

 

 

 

___________________________________

Assistant City Attorney