Legislation #: 001457 Introduction Date: 10/26/2000
Type: Ordinance Effective Date: 11/19/2000
Sponsor: None
Title: Authorizing a $447,822.00 contract with The Larkin Group for Contract No. 7608 Design for the Eastern Clay County Transmission Main; and authorizing expenditure of funds.

Legislation History
DateMinutesDescription
10/26/2000

Prepare to Introduce

10/26/2000

Referred Operations Committee

11/1/2000

Do Pass

11/2/2000

Assigned to Third Read Calendar

11/9/2000

Passed


View Attachments
FileTypeSizeDescription
No attachment(s) found

Printer Friendly Version

 

ORDINANCE NO. 001457

 

Authorizing a $447,822.00 contract with The Larkin Group for Contract No. 7608 Design for the Eastern Clay County Transmission Main; and authorizing expenditure of funds.

 

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

 

Section 1. That the Director of Water Services is hereby authorized to execute, on behalf of Kansas City, a $447,822.00 contract for design of the Eastern Clay County Transmission Main. A copy of the contract is on file in the office of the Director of Water Services.

 

Section 2. That the Director of Water Services is further authorized to expend up to the sum of $447,822.00 previously appropriated to Account No. 01-801-080-7703-T Water Main Const/Rehab to satisfy the cost of this contract.

 

__________________________________________________________________

 

I hereby certify that there is a balance, otherwise unencumbered, to the credit of the appropriation to which the foregoing expenditure is to be charged, and a cash balance, otherwise unencumbered, in the treasury, to the credit of the fund from which payment is to be made, each sufficient to meet the obligation hereby incurred.

 

 

 

____________________________________

Director of Finance

 

Approved as to form and legality:

 

 

 

___________________________________

Assistant City Attorney