Legislation #: 050129 Introduction Date: 2/3/2005
Type: Ordinance Effective Date: none
Sponsor: None
Title: Amending an amendment to a previously approved development plan District R-5-p on approximately a 6 acre tract of land generally located at the southeast corner of N.E. 80th Street and N. Spruce Street. (12542-P-7)

Legislation History
DateMinutesDescription
2/3/2005 Filed by the Clerk's office
2/3/2005 Referred to Planning, Zoning & Economic Development Committee
2/23/2005 Hold On Agenda (3/9/2005)
3/9/2005 Advance and Do Pass as a Committee Substitute, Debate
3/10/2005 Passed as Substituted

View Attachments
FileTypeSizeDescription
Maps 0K Plat Map on file with ordinance in City Clerk's office
050129 Mailing List.pdf Plan Mailing List 54K Mailing List
050129.pdf Authenticated 149K Authenticated
publicnotice050111,112,128,130,131.pdf Advertise Notice 49K PUBLIC NOTICE
C012542P7_STAFFREPORT_01-04-05.doc Staff Report 68K Staff Report
C012542P7_Fact Sheet.doc Fact Sheet 57K Fact Sheet

Printer Friendly Version

COMMITTEE SUBSTITUTE FOR ORDINANCE NO. 050129

 

Amending an amendment to a previously approved development plan District R-5-p on approximately a 6 acre tract of land generally located at the southeast corner of N.E. 80th Street and N. Spruce Street. (12542-P-7)

 

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

 

Section A. That an amendment to a previously approved development plan in District R-5-p (High Apartments Limited District) on approximately a 6 acre tract of land generally located at the southeast corner of N.E. 80th Street and N. Spruce Street, and more specifically described as follows:

 

All that part of the Northwest Quarter of Section 17, Township 51 North, Range 32 West, in the City of Kansas City, Clay County, Missouri, being more particularly described as follows: Commencing at the Northwest Corner of the Northwest Quarter of said Section 7; thence South 885757 East, along the North line of the Northwest Quarter of said Section 17, a distance of 459.00 feet; thence South 004018 East, a distance of 30.00 feet to the intersection of the South right-of-way line of NE 80th Street, as now established and recorded in the Office of the Register of Deeds, Clay County, Missouri, in Book 508 at Page 75 and the East right-of-way line of North Spruce Avenue, as now established and recorded in the Office of the Register of Deeds, Clay County, Missouri, in Book 508 at Page 75, said point also being the Point of Beginning of this description; thence South 885757 East, along said South right-of-way line of NE 80th Street, 30.00 feet South of and parallel with the North line of the Northwest Quarter of said Section 17, a distance of 556.56 feet; thence South 000338 West, a distance of 138.88 feet; thence South 573825 East, a distance of 124.03 feet; thence South 895521 East, a distance of 452.91 feet; thence North 773023 East, a distance of 82.49 feet; thence South 561742 West, a distance of 424.07 feet; thence North 894443 West, a distance of 297.02 feet; thence North 002450 East, a distance of 136.19 feet; thence North 885757 West, a distance of 549.16 feet to a point on said East right-of-way line of North Spruce Avenue; thence North 004015 East, along said East right-of-way line of North Spruce Avenue, a distance of 286.01 feet to the Point of Beginning, and containing 6.0294 Acres, more or less.

 

is hereby approved, subject to the following conditions:

 

1.                  That the developer cause the area to be platted and processed in accordance with Chapter 66, Code of Ordinances of the City of Kansas City, Missouri, commonly known as the Subdivision Regulations.

 

2.                  That the developer submit a storm drainage study for the entire development to the City Engineer's Office for approval when the final plat is submitted and that the developer make any necessary improvements as required by the City Engineer's Office.

 

3.                  That the developer submit plans for grading and siltation and erosion control to the City Engineer's Office for approval prior to beginning any construction activities.

 

4.                  That the developer secure a land disturbance permit from the Department of Public Works prior to beginning any construction, grading, clearing or grubbing activities, if the disturbed area exceeds one acre.

 

5.                  That the developer dedicate 60 feet of right of way from centerline on the east half of N. Spruce and for future Maplewoods Parkway.

 

6.                  That the developer install hard surface roads and provide for fire protection as required by the Fire Department prior to construction beyond foundations.

 

7.                  That the developer extend sanitary sewers as required by the Department of Public Works.

 

8.                  That the developer extend water mains as required by the Water Services Department.

 

9.                  That the developer dedicate 30 feet of right of way from centerline on the south side of N.E. 80th Street and as necessary for the roundabout as required by the Department of Public Works.

 

10.              That the developer improve the south half of N.E. 80th Street to collector street standards including construction of curb, gutter, sidewalks and installation of streetlights, as required by the Department of Public Works.

 

11.              That the developer improve the east half of N. Spruce Avenue to collector street standards, including curb, gutter, sidewalks and installation of streetlights, as required by the Department of Public Works and the Parks and Recreation Department and/or in accordance with the most current adopted revisions to the Major Street Plan for N. Spruce Avenue.

 

12.              That the developer secure a floodplain certificate from the Department of Codes Administration prior to beginning any construction activities within the floodplain.

 

13.              That the developer show the limits of the floodplain on the final plat as required by the Department of Public Works.

 

14.              That the developer submit a final plan to the City Plan Commission for approval, including plans for building materials and elevations, signage, grading, lighting (including a photometric study showing 0 footcandles at the property lines) and landscaping.

 

15.              That the developer obtain any required approval from the Board of Zoning Adjustment for the offices and signage.

 

A copy of said amendment is on file in the office of the City Clerk with this ordinance, which is attached hereto and made a part hereof.

 

Section B. That the Council finds and declares that before taking any action on the proposed amendment hereinabove, all public notices and hearings required by the Zoning Ordinance have been given and had.

 

_____________________________________________

 

I hereby certify that as required by Chapter 80, Code of Ordinances, the foregoing ordinance was duly advertised and public hearings were held.

 

 

___________________________________

Secretary, City Plan Commission

 

Approved as to form and legality:

 

 

___________________________________

M. Margaret Sheahan Moran

Assistant City Attorney