ORDINANCE NO. 920462
Authorizing a First Supplement to Agreement No. 900632 in
the amount of $1,842,689.00 with Harrington and Cortelyou, Inc. for engineering
services relating to replacement of the Chouteau Bridge.
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of Public Works is
hereby authorized to enter into and execute on behalf of Kansas City, a First
Supplement to Agreement No. 900632 between Harrington and Cortelyou, Inc. and
Kansas City, Missouri, relating to engineering services for the replacement of
the Chouteau Bridge over Missouri River to be completed in three phases:
Phase A: Feasibility Study Phase B: Preliminary and
Final Engineering Design Phase C: Construction Observation
to begin Phase B, Project No. 5352, Council District 1,
Kansas City, Missouri. The said Agreement shall be essentially in the form
which is attached and incorporated herein by reference.
Section 2. That the Director of Public Works is
hereby authorized to expend the sum of $1,842,689.00 from funds heretofore
appropriated to Account No. 6-40420-T as and for consideration in the aforesaid
First Supplement to Agreement No. 900632.
________________________________________________________
I hereby certify that there is a balance, otherwise
unencumbered, to the credit of the appropriation to which the foregoing
expenditure is to be charged, and a cash balance, otherwise unencumbered, in
the treasury, to the credit of the fund from which payment is to be made, each
sufficient to meet the obligation hereby incurred.
___________________________________
Director of Finance
Approved as to form and
legality:
___________________________________
Assistant City Attorney