Legislation #: 140526 Introduction Date: 7/31/2014
Type: Ordinance Effective Date: none
Sponsor: None
Title: Declaring it necessary to change and re-establish the grades of North Jackson Avenue from Northeast Vivion Road to the Gladstone City limits, for the “N. Jackson Avenue Street _ Storm Sewer Improvements”; and directing the City Clerk to cause a notice to be published as provided for herein.

Legislation History
DateMinutesDescription
7/8/2014 Filed by the Clerk's office
7/31/2014 Referred to Transportation & Infrastructure Committee
8/14/2014 Advance and Do Pass, Consent
8/14/2014 Passed

View Attachments
FileTypeSizeDescription
140526.pdf Authenticated 276K Authenticated
140526 Fact Sheet.pdf Fact Sheet 105K Fact Sheet

Printer Friendly Version

ORDINANCE NO. 140526

 

Declaring it necessary to change and re-establish the grades of North Jackson Avenue from Northeast Vivion Road to the Gladstone City limits, for the “N. Jackson Avenue Street & Storm Sewer Improvements”; and directing the City Clerk to cause a notice to be published as provided for herein.

 

WHEREAS, the Council finds that for the public good it is necessary that the grades on North Jackson Avenue from N. Jackson Avenue, all in Kansas City, Clay County, Missouri, be changed and re-established; and

 

WHEREAS, the Council further finds the Director of Public Works, as evidenced by her issuing a Declaration of Necessity, No. 5515, adopted and entered on August 1st, 2013, has caused the plans and specifications for Project Number 89008251 “N. Jackson Avenue Street & Storm Sewer Improvements” to be prepared; NOW, THEREFORE,

 

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

 

Section 1. That finding it necessary to change and re-establish grades on North Jackson Avenue, from Northeast Vivion Road to the Gladstone City limits, all being in Kansas City, Clay County, Missouri, the Council hereby directs that the City Clerk cause a notice of said grade changes to be published in the newspaper doing the city printing, on each day of issue of said newspaper for a period of ten (10) days, starting on or about the date following the passage of this ordinance, and providing a period of thirty (30) days for remonstrance starting the same day as the first day of the publication.

 

Section 2. That said grade changes shall be of the nature described and specified in, and shall be done in accordance with the plans and specifications prepared and certified by the City Engineer under the supervision of the Director of Public Works and identified as KCMO Project Number 89008251 “N. Jackson Avenue Street & Storm Sewer Improvements”, the same being on file in the Office of the Director of Public Works and being incorporated herein by reference.

 

Section 3. That the establishing of the grade of the Right of Way is hereby authorized to commence when this ordinance becomes effective, and shall be built in accordance with the plans and specifications as described in Section 2 of this ordinance; locating and defining the grade points of said streets on the proposed project centerline stationing, as found on said plans, said centerline being described by distance and bearings, control points, and stationing; said grade points being connected by straight grades (tangents) or vertical curves between such grade points, the elevations of which are herein given below in feet (NAVD88 directrix), along with other pertinent alignment data, to-wit:

 

Street grades for North Jackson Avenue: Begin construction at Sta. 10+63.56, match grade as shown on plans.

 

All grade points are on the centerline of North Jackson Avenue, as herein described, and as found in said plans in the office of the Director of Public Works, and are shown to wit:

 

Centerline, North Jackson Avenue; Point of Commencement of Centerline at Station 10+63.56:

 

State Plane Coordinates (SPC) N 1,100,187.2390, E 2,780,080.5282

 

Station Slope Elevation

 

10+63.56, VPI 907.37

11+50.00, VPC +5.00 percent 911.70

13+00.00, VPI 919.20

14+50.00, VPT -7.84 percent

 

Length of vertical curve is 300 feet.

 

18+53.00, VPC -7.84 percent 875.84

20+33.00, VPI 861.73

22+13.00, VPRC +1.00 percent 863.53

23+63.00, VPI 865.03

25+13.00, VPRC -7.00 percent 854.53

25+60.00, VPI 851.24

26+07.00, VPT -2.28 percent 850.17

 

Length of vertical curve from VPC to VPRC is 360 feet.

Length of vertical curve from VPRC to VPRC is 300 feet.

Length of vertical curve from VPRC to PVT is 94 feet.

 

28+00.00, VPI 845.77

-2.41 percent

28+20.00, VPI 845.29

-3.17 percent

28+80.00, VPI 843.38

28+88.00, VPC -1.00 percent 843.30

29+78.00, VPI 842.40

30+68.00, VPT +7.76 percent 849.39

 

Length of vertical curve is 180 feet.

 

32+35.00, VPC +7.76 percent 862.35

33+00.00, VPI 867.39

33+65.00, VPT +4.52 percent 870.33

 

Length of vertical curve is 130 feet.

 

34+35.45, VPI 873.51

+2.03

34+95.45, VPI 874.73

 

Existing Grade – End of Construction for North Jackson Avenue.

SPC N 1,102,618.8563, E 2,780,116.6548

 

Street grades for NE 52nd Terrace: Begin construction at Sta. 9+00.00, match grade as shown on plans.

 

All grade points are on the centerline of NE 52nd Terrace, as herein described, and as found in said plans in the office of the Director of Public Works, and are shown to wit:

 

Centerline, NE 52nd Terrace:

Point of Commencement of Centerline at Station 9+00.00,

NE 52nd Terrace intersects the centerline of North Jackson Avenue at Station 13+60.40. Match the grade as shown on plans.

 

NE 52nd Terrace centerline Station 9+00.00:

SPC N 1,100,485.4921, E 2,779,984.9483

 

Station Slope Elevation

 

9+00.00, VPC -2.37 percent 915.51

9+20.00, VPI 915.03

9+40.00, VPRC -5.00 percent 914.03

 

9+60.00, VPI 913.03

9+80.00, VPT -2.00 percent 912.63

 

Length of vertical curve from VPC to VPRC is 40 feet.

Length of vertical curve from VPRC to PVT is 40 feet.

 

9+86.00, VPI 912.51

+2.00 percent

10+00.00, VPI 912.79

 

Existing Grade – End of Construction for NE 52nd Terrace.

SPC N 1,100,484.0055, E 2,780,084.9373

 

Street grades for NE 54th Street: Begin construction at Sta. 8+15.00; match grade as shown on plans.

 

All grade points are on the centerline of NE 54th Street, as herein described, and as found in said plans in the office of the Director of Public Works, and are shown to wit:

 

Centerline, NE 54th Street:

Point of Commencement of Centerline at Station 8+15.00.

NE 54th Street intersects the centerline of North Jackson Avenue at Station 20+42.60. Match the grade as shown on plans.

 

NE 54th Street centerline Station 8+15.00:

SPC N 1,101,168.5510, E 2,779,910.0872

 

Station Slope Elevation

 

Existing Grade -4.33 percent

8+15.00, VPC -3.00 percent 875.84

8+40.00, VPI 875.09

8+65.00, VPT -10.83 percent 872.38

 

Length of vertical curve from VPC to VPT is 50 feet.

 

9+20.00, VPC -8.92 percent 866.42

9+45.00, VPI 864.19

9+70.00, VPT +2.24 percent 864.75

 

Length of vertical curve from VPC to VPT is 50 feet.

9+86.00, VPI 865.11

+2.00 percent

10+00.00, VPI 865.39

 

Existing Grade – End of Construction for NE 54th Street.

SPC N 1,101,165.8027, E 2,780,095.0667

 

__________________________________________________

 

Approved as to form and legality:

 

 

______________________________

Nelson V. Munoz