ORDINANCE NO. 941029
Authorizing the Director of Public Works to enter into a
Second Supplement to Agreement No. 930766 with Cook, Flatt, and Strobel for
engineering services for the Rockwell Lane Bridge over Brush Creek replacement
project; and authorizing the expenditure of $4,320.00 in previously
appropriated funds therefor.
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the Director of Public Works is
hereby authorized to enter into and execute, on behalf of Kansas City, a Second
Supplement to Agreement No. 930766, with Cook, Flatt, and Strobel for
engineering services in connection with the replacement of the Rockwell Lane
Bridge over Brush Creek to be completed in two phases:
Phase A: Engineering Design Services Phase B:
Construction Observation
to expand the scope of Phase A, Kansas City, Missouri,
Council District 4, Project No. 5377. The agreement shall be essentially in
the form which is attached hereto and incorporated herein by reference.
Section 2. That the Director of Public Works is
hereby authorized to expend the sum of $4,320.00 from funds heretofore
appropriated to Account No. 94-399-089-7411-T as and for consideration for the
Second Supplement.
_____________________________________________
I hereby certify that there is a balance, otherwise
unencumbered, to the credit of the appropriation to which the foregoing
expenditure is to be charged, and a cash balance, otherwise unencumbered, in
the treasury, to the credit of the fund from which payment is to be made, each
sufficient to meet the obligation hereby incurred.
___________________________________
Director of Finance
Approved as to form and
legality:
___________________________________
Assistant City Attorney