KC Skyline

City Clerk Web Search

Search the Ordinances:

Legislation #: 090714 Introduction Date: 8/13/2009
Type: Ordinance Effective Date: 8/27/2009
Sponsor: COUNCILMEMBER JOHNSON
Title: Authorizing the Director of Water Services Department to enter into a $1,663,417.00 contract with Radmacher Brothers Excavating Company, Inc. for the Troost at Brush Creek – Sanitary Sewer, Channel and Pedestrian Bridge Improvements; authorizing the Director of Water Services to expend $1,800,000.00 for the project; authorizing the Director of Finance to return unexpended appropriations to the appropriate account; and recognizing an emergency.

Legislation History
DateMinutesDescription
8/13/2009 Filed by the Clerk's office
8/13/2009 Referred to Transportation and Infrastructure Committee
8/27/2009 Advance and Do Pass, Debate
8/27/2009 Passed

View Attachments
FileTypeSizeDescription
http://kansascity.granicus.com/ViewSearchResults.php?view_id=2&keywords=090714 Video Link 0K http://kansascity.granicus.com/ViewSearchResults.php?view_id=2&keywords=090714
090714.pdf Authenticated 80K AUTHENTICATED
090714.doc Docket Memo 30K Docket Memo
fact sheet.XLS Advertise Notice 50K fact sheet
fiscal note.xls Advertise Notice 45K fiscal note
docket memo.pdf Advertise Notice 72K docket memo

Printer Friendly Version

ORDINANCE NO. 090714

 

Authorizing the Director of Water Services Department to enter into a $1,663,417.00 contract with Radmacher Brothers Excavating Company, Inc. for the Troost at Brush Creek Sanitary Sewer, Channel and Pedestrian Bridge Improvements; authorizing the Director of Water Services to expend $1,800,000.00 for the project; authorizing the Director of Finance to return unexpended appropriations to the appropriate account; and recognizing an emergency.

 

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

Section 1. That the Director of Water Services Department is hereby authorized to execute, on behalf of Kansas City, Contract No. 162, Troost at Brush Creek Sanitary Sewer, Channel and Pedestrian Bridge Improvements, in the amount of $1,663,417.00 with Radmacher Brothers Excavating Company, Inc. to provide for bridge construction, sidewalk/trail construction, retaining walls, sanitary sewer construction, pedestrian lighting, erosion control, demolition and other associated work in the area of Troost and Brush Creek. This project will be performed in Jackson County, Kansas City, Missouri. A copy of this contract is on file in the office of the Director of Water Services. 

Section 2. That the Director of Water Services is authorized to expend up to the sum of $1,800,000.00, from funds previously appropriated to Account No. AL-8183-807521-B, Brush Creek Improvements, including contingencies, to satisfy the cost of this contract.

 

Section 3. That upon completion of the final costs of this contract, the Director of Finance is hereby authorized to return the unexpended portion of this appropriation to the Fund Balance from which it was derived.

 

Section 4. That this ordinance, relating to the design, repair, maintenance or construction of a public improvement, is recognized as an emergency measure within the provisions of Section 503 of the City Charter and shall take effect in accordance with that section.

 

__________________________________________________

  


I hereby certify that there is a balance, otherwise unencumbered, to the credit of the appropriation to which the foregoing expenditure is to be charged, and a cash balance, otherwise unencumbered, in the treasury, to the credit of the fund from which payment is to be made, each sufficient to meet the obligation hereby incurred.

 

 

___________________________________

Jeffrey A. Yates

Director of Finance

 

Approved as to form and legality:

  

 

___________________________________

Nelson Munoz

Assistant City Attorney