ORDINANCE NO. 920303
Authorizing contracts with Musselman & Hall
Contractors, Inc. in the amounts of $116,307.00 for west dock streetscape work;
$265,180.00 for exhibit hall streetscape work; and $198,561.00 for conference center
streetscape work at the Bartle Hall Expansion Project, 301 West 13th Street.
BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:
Section 1. That the work of providing west dock
streetscape construction, exhibit hall streetscape construction and conference
center streetscape construction at the Bartle Hall Expansion Project, 301 West
13th Street, Kansas City, Missouri, is hereby provided for and authorized.
Section 2. That the work shall be done in
accordance with the plans, specifications and the contracts therefor between
Kansas City, Missouri, through its Director of Public Works, and Musselman
& Hall Contractors, Inc. in the amount of $116,307.00 for west dock
streetscape work; in the amount of $265,180.00 for exhibit hall streetscape
work, and in the amount of $198,561.00 for conference center streetscape work,
which contracts are hereby approved and confirmed. Copies of the said
contracts are on file in the office of the Director of Public Works and are
incorporated herein by reference.
Section 3. That the Director of Public Works is
hereby authorized to expend the sum of $591,649.00 from funds heretofore
appropriated to Account No. 686-40522T as and for consideration in the
aforesaid contracts and contingencies related thereto.
_______________________________________________________
I hereby certify that there is a balance, otherwise
unencumbered, to the credit of the appropriation to which the foregoing
expenditure is to be charged, and a cash balance, otherwise unencumbered, in
the treasury, to the credit of the fund from which payment is to be made, each
sufficient to meet the obligation hereby incurred.
___________________________________
Director of Finance
Approved as to form and
legality:
___________________________________
Assistant City Attorney