061162
Authorizing a $824,175.05 Fourth Amendment to Agreement No. CS960629 with HDR Engineering, Inc., for engineering design services for Project No. 89005406–23rd Street Viaduct; authorizing the City Manager to expend $824,175.05 for the project; designating requisitioning authority; and recognizing an emergency.


OPERATIONS COMMITTEE recommends "ADVANCE AND DO PASS, DEBATE"
Ralph Davis, CIMO, testified on behalf of this ordinance. This is the last piece of the design for the project. This is a five ton bridge. The bridge is still open at this time.
Ayes: 3 - Riley, Eddy, Hermann
Nays: 0

061164
Authorizing the Director of Public Works to enter into a $1,549,247.45 contract with Loch Sand and Construction Company for Project No. 89005445; authorizing the Director of Public Works to amend and increase this contract; authorizing the City Manager to expend appropriated funds; and designating requisitioning authority.


OPERATIONS COMMITTEE recommends "ADVANCE AND DO PASS, DEBATE"
Ralph Davis, CIMO, tesitfied on behalf of this ordinance.
Ayes: 3 - Riley, Eddy, Hermann
Nays: 0

061165
Reducing Blue River project appropriations in the Capital Improvement Fund totaling $1,062,000.00 from the Department of Public Works; reappropriating a total of $1,062,000.00 from the Unappropriated Fund Balance of the Capital Improvements Fund to the Department of Water Services; authorizing transfer between accounts of encumbrances relating to Special Projects; and designating requisitioning authority.


OPERATIONS COMMITTEE recommends "ADVANCE AND DO PASS, DEBATE"
Jim Mellum, Water Services, tesitifed on behalf of this ordinance.
Ayes: 3 - Riley, Eddy, Hermann
Nays: 0

061123
Authorizing an increase in the contract contingency in the amount of $285,000.00 for a contract with Orr Construction Management, Inc. for Project No. 89000404, and authorizing the City Manager to expend $285,000.00 from previously appropriated funds.


OPERATIONS COMMITTEE recommends "ADVANCE AND DO PASS, DEBATE"

Ayes: 3 - Riley, Eddy, Hermann
Nays: 0
 
 Staff from the Budget Office will give a status report on the Red Light Camera RFP.