Legislation #: 190333 Introduction Date: 4/25/2019
Type: Ordinance Effective Date: 5/3/2019
Sponsor: None
Title: Authorizing a $1,430,850.00 Design Professional Services Contract with HDR Engineering Inc., for the Secondary Electrical Switchgear Improvements at the Water Treatment Plant Project; and recognizing this ordinance as having an accelerated effective date.

Legislation History
DateMinutesDescription
4/25/2019 Filed by the Clerk's office
4/25/2019 Referred to Transportation & Infrastructure Committee
5/2/2019 Advance and Do Pass, Debate
5/2/2019 Passed

View Attachments
FileTypeSizeDescription
190333.pdf Authenticated 49K Authenticated Ordinance
9489 Fact Sheet - Revised 05-02-19.pdf Fact Sheet 31K 9489 Revied Fact Sheet
Ordinance 190333-Docket Memo 9489.pdf Docket Memo 16K 190333 Docket Memo
9489 DPS Contract.pdf Contracts 535K 9489 DPS Contract
9489 Fact Sheet.xlsx Fact Sheet 23K 9489 Fact Sheet
9489 Fiscal Note.xlsx Fiscal Note 17K 9489 Fiscal Note

Printer Friendly Version

ORDINANCE NO. 190333

 

Authorizing a $1,430,850.00 Design Professional Services Contract with HDR Engineering Inc., for the Secondary Electrical Switchgear Improvements at the Water Treatment Plant Project; and recognizing this ordinance as having an accelerated effective date.

 

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

 

Section 1. That the Director of Water Services is authorized to execute Contract No. 9489 in the amount of $1,430,850.00 with HDR Engineering Inc., for the Secondary Electrical Switchgear Improvements at the Water Treatment Plant Project, Project No. 80002134.  A copy of this contract is on file in the office of Water Services.

 

Section 2. That the Director of the Water Services Department is authorized a maximum expenditure of $1,430,850.00 from the following accounts to satisfy the cost of this contract:

 

AL-8076-807714-B-611040-80002134 Treatment Facilities $ 800,000.00

20-8010-807714-B-611040-80002134 Treatment Facilities 630,850.00

TOTAL $1,430,850.00

 

Section 3. That this ordinance, relating to the design, repair, maintenance or construction of a public improvement, is recognized as an ordinance with an accelerated effective date as provided by Section 503(a)(3)(D) of the City Charter and shall take effect in accordance with Section 503, City Charter.

 

_____________________________________

  

I hereby certify that there is a balance, otherwise unencumbered, to the credit of the appropriation to which the foregoing expenditure is to be charged, and a cash balance, otherwise unencumbered, in the treasury, to the credit of the fund from which payment is to be made, each sufficient to meet the obligation hereby incurred.

  

 

________________________________

Randall J. Landes

Director of Finance

 

Approved as to form and legality:

 

   

________________________________

Mark P. Jones

Assistant City Attorney