ORDINANCE NO. 050549
Authorizing a $275,000.00
contract contingency increase with Kraus-Anderson Construction Company for
additional service corridors renovation work in connection with the Bartle Hall
Renovation Improvements project; and authorizing the expenditure of previously
appropriated funds in the amount of $275,000.00.
BE IT ORDAINED
BY THE COUNCIL OF KANSAS CITY:
Section 1. That
the Director of Public Works is hereby authorized to increase the contingency
for Contract No. PW040003 with. Kraus-Anderson Construction Company for
additional service corridors construction work in connection with the Bartle
Hall Renovation Improvements, Project No. 284-03030-6, which was approved by Ordinance No. 040784, passed July 15, 2004, from $2,398,000.00 to $2,673,000.00 in the additional amount of $275,000.00.
Section 2. That
the Director of Public Works is hereby authorized to expend the additional sum
of $275,000.00 from funds appropriated to Account No. AL-3400-897240-B as and
for consideration in the aforesaid contract contingency increase.
_____________________________________________
I hereby certify that
there is a balance, otherwise unencumbered, to the credit of the appropriation
to which the foregoing expenditure is to be charged, and a cash balance,
otherwise unencumbered, in the treasury, to the credit of the fund from which
payment is to be made, each sufficient to meet the obligation hereby incurred.
___________________________________
Wanda
Gunter
Acting
Director of Finance
Approved
as to form:
___________________________________
Mark
P. Jones
Assistant City Attorney