ORDINANCE NO. 140556
Authorizing the Director of Water
Services to enter into a $1,629,000.00 contract with Foley Company for the
Universal Avenue Storm Sewer Improvements – Phase 2 – Milwaukee Pump Station
Improvements project.
BE IT ORDAINED BY THE COUNCIL OF
KANSAS CITY:
Section 1. That
the Director of Water Services Department is hereby authorized to execute, on
behalf of Kansas City, Contract No. 263, Project No. 82000088, with Foley
Company, in the amount of $1,629,000.00 for Phase 2 for the Universal Avenue
Storm Sewer Improvements to the Milwaukee Pump Station, including replacement
of in-kind pumps, Supervisory Control and Data Acquisition system installation,
and other appurtenances, located in Jackson County, Kansas City, Missouri.
A copy of this contract is on file in the office of the Director of Water
Services.
Section 2. That
the Director of Water Services is authorized to expend up to the sum of
$1,875,000.00, from Account No. 15-8200-807760-B-611060, Stormwater
Construction, to satisfy the costs of this project.
_____________________________________________
I
hereby certify that there is a balance, otherwise unencumbered, to the credit
of the appropriation to which the foregoing expenditure is to be charged, and a
cash balance, otherwise unencumbered, in the treasury, to the credit of the
fund from which payment is to be made, each sufficient to meet the obligation
hereby incurred.
________________________________
Randall J. Landes
Director of Finance
Approved as to form and legality: