ORDINANCE NO. 050882
Authorizing a $20,368.33 contract
contingency increase with Audrie Seeley & Co., Inc., for the construction
of storm drainage improvements through Woodbridge Subdivision; and authorizing
the City Manager to expend an additional $20,368.33 for the project.
BE IT ORDAINED
BY THE COUNCIL OF KANSAS CITY:
Section 1. That
the City Manager is hereby authorized to increase the contingency by $20,368.33
for Contract No. 020130 with Audrie Seeley & Co., Inc., to match the
revised contract amount of $860,368.33 at contract-closeout in connection with
additional construction work involving storm drainage improvements through
Woodbridge Subdivision, as part of the Public Improvements Tax Years 12 through
19 projects in Council District 6, Kansas City, Missouri, Project No. 309-089-6600-3520, which was approved by Ordinance
No. 030076, passed February 13, 2003.
Section 2. That the
City Manager is hereby authorized to expend the additional sum of $20,368.33
from funds previously appropriated to Account No. 06-3090-896600-B for the
aforesaid contract contingency increase.
_____________________________________________
I hereby certify that
there is a balance, otherwise unencumbered, to the credit of the appropriation
to which the foregoing expenditure is to be charged, and a cash balance,
otherwise unencumbered, in the treasury, to the credit of the fund from which
payment is to be made, each sufficient to meet the obligation hereby incurred.
___________________________________
Wanda