ORDINANCE NO. 160916
Authorizing a $1,324,971.00
construction contract with Blue Nile Contractors, Inc., for the replacement of
water mains in the area of Bristol Avenue to Booth Avenue, E. 47th Street to
73rd Street; authorizing a maximum expenditure of $1,460,000.00; and
recognizing this ordinance as having an accelerated effective date.
BE IT ORDAINED BY THE COUNCIL OF
KANSAS CITY:
Section 1. That
the Director of the Water Services Department is
authorized to execute Contract No. 9164 in the amount of $1,324,971.00 with
Blue Nile Contractors, Inc., for the replacement of water mains in the area of Bristol Avenue to Booth Avenue, E. 47th Street to 73rd
Street, Project No. 80001876. A copy of the contract is on file in the
office of the Water Services Department.
Section 2. That
the Director of the Water Services Department is authorized a maximum expenditure
of $1,460,000.00, from Account No. 17-8010-807705-B-611060-80001876, Water Main
Replacement Program, to satisfy the cost of this contract.
Section 3. That this ordinance, relating to the
design, repair, maintenance or construction of a public improvement, is
recognized as an ordinance with an accelerated effective date as provided by
Section 503(a)(3)(D) of the City Charter and shall take effect in accordance
with Section 503, City Charter.
_____________________________________________
I hereby certify
that there is a balance, otherwise unencumbered, to the credit of the
appropriation to which the foregoing expenditure is to be charged, and a cash
balance, otherwise unencumbered, in the treasury, to the credit of the fund
from which payment is to be made, each sufficient to meet the obligation hereby
incurred.
________________________________
Randall J. Landes
Director of Finance
Approved as to form and legality:
________________________________
Mark P. Jones
Assistant City Attorney