KC Skyline

City Clerk Web Search

Search the Ordinances:

Legislation #: 960047 Introduction Date: 1/18/1996
Type: Ordinance Effective Date: 2/18/1996
Sponsor: None
Title: Amending Chapter 2, Code of Ordinances, by repealing Sections 2-1723 and 2-1724 and enacting in lieu thereof one new Section 2-1723.

Legislation History
DateMinutesDescription
1/18/1996

Prepare to Introduce

1/18/1996

Referred City Operations Committee

1/24/1996

Hold On Agenda

1/31/1996

Do Pass

2/1/1996

Assigned to Third Read Calendar

2/8/1996

Passed


View Attachments
FileTypeSizeDescription
No attachment(s) found

Printer Friendly Version

 

ORDINANCE NO. 960047

 

Amending Chapter 2, Code of Ordinances, by repealing Sections 2-1723 and 2-1724 and enacting in lieu thereof one new Section 2-1723.

 

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

 

Section 1. That Sections 2-1723 and 2-1724 of the Code of Ordinances designated engineering services for sanitary sewer project is hereby amended by repealing Section 2-1723 entitled Appropriation for engineering cost and Section 2-1724, entitled Appropriation for administrative cost and enacting in lieu thereof one new Section 2-1723 of like subject matter, said section to read as follows:

 

Sec. 2-1723. Appropriation and apportionment of engineering cost and administrative cost.

 

(a) When any public improvement, the cost of which is to be apportioned and assessed against benefited properties, is authorized, an appropriation may be made to cover the cost of engineering and administrative services required as a part of the improvement. Such engineering and administrative services may be provided either by the city engineer or by consulting engineers, or by any combination of the city engineer's forces and any consulting engineer's forces. In the case of street improvements, when the work is performed only by the city engineer's forces, an engineering and administrative appropriation of 16 percent of the construction cost shall be made. When consulting engineers are employed to supplement the city engineer's staff for street improvements, an appropriation equal to the actual cost of the engineering performed by the consulting engineer plus an amount equal to 5 percent of the construction cost for engineering and administration performed by the city engineer shall be made. In the case of sewer improvements, when the work is performed by city engineer, by consulting engineer, or by any combination of the city engineer's forces and any consulting engineer's forces, an engineering and administrative appropriation of 25 percent of the construction cost shall be made.

 

(b) In the apportionment of the cost of an improvement for assessment purposes, there shall be added to the construction cost for projects the following: For engineering and administrative services on street improvements, when the work is performed only by the city engineer's forces, there shall be added to the construction cost an amount equal to 16 percent of the construction cost; when street improvements require services of consulting engineers, there shall be added to the construction cost of the project an amount equal to the actual cost for services performed by consulting engineers plus 5 percent of the construction cost for services provided by the city engineer. For engineering and administrative services on sewer improvements, when the work is performed by the city engineer, by consulting engineer, or by any combination of the city engineer's forces and any consulting engineer's forces there shall be added to the construction cost an amount equal to 25 percent of the construction cost. ____________________________________________

 

Approved as to form and legality:

 

___________________________________

Assistant City Attorney