KC Skyline

City Clerk Web Search

Search the Ordinances:

Legislation #: 081208 Introduction Date: 12/4/2008
Type: Ordinance Effective Date: 12/28/2008
Sponsor: None
Title: Authorizing execution of Amendment No. 1 to the Design Agreement with the U.S. Army Corps of Engineers relating to the design of the Swope Park Industrial Area Flood Damage Reduction Project; and authorizing the Director of Water Services to expend $100,000.00 for the City's share of the amendment.

Legislation History
DateMinutesDescription
12/1/2008 Filed by the Clerk's office
12/4/2008 Referred to Transportation and Infrastructure Committee
12/11/2008 Do Pass
12/11/2008 Add to Consent Docket
12/18/2008 Passed

View Attachments
FileTypeSizeDescription
081208.pdf Authenticated 64K Authenticated
Swope Park PED Amendment Fact Sheet.xls Fact Sheet 49K Swope Park Industrial Park Amendment 1 Fact Sheet
Swope Park PED Amendment 1 Fiscal Note.xls Fiscal Note 37K Swope Park Industrial Area Amendment 1 Fiscal Note

Printer Friendly Version

ORDINANCE NO. 081208

 

Authorizing execution of Amendment No. 1 to the Design Agreement with the U.S. Army Corps of Engineers relating to the design of the Swope Park Industrial Area Flood Damage Reduction Project; and authorizing the Director of Water Services to expend $100,000.00 for the City's share of the amendment.

 

WHEREAS, the City and the U.S. Army Corps of Engineers executed a $1,000,000.00 cost-share Design Agreement following approval of Ordinance No. 030886 on August 28, 2003, for the provision of engineering and design services in connection with the Swope Park Industrial Area Flood Damage Reduction Project;

 

WHEREAS, an Amendment No. 1 is required to continue design of the Swope Park Industrial Area Flood Damage Reduction Project; and

 

WHEREAS, since the City and the U.S. Army Corps of Engineers share the costs of design on a 25% local and 75% federal basis, the Citys cost for this amendment is $100,000.00 and the federal share is $300,000.00; NOW, THEREFORE,

 

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

 

Section 1. That the Director of Water Services is hereby authorized to execute, on behalf of the City, Amendment No. 1 to the Design Agreement with the U.S. Army Corps of Engineers for the Swope Park Industrial Area Flood Damage Reduction Project, Project No. 89002672, and to expend $100,000.00 from funds previously appropriated to Account No. 09-3090-807533-B, for this purpose. A copy of the Design Agreement Amendment No. 1 is on file in the office of the Director of Water Services.

 

_____________________________________________

 

I hereby certify that there is a balance, otherwise unencumbered, to the credit of the appropriation to which the foregoing expenditure is to be charged, and a cash balance, otherwise unencumbered, in the treasury, to the credit of the fund from which payment is to be made, each sufficient to meet the obligation hereby incurred.

 

 

___________________________________

Jeffrey A. Yates

Director of Finance

 

Approved as to form and legality:

 

 

___________________________________

Cecilia OConnor Abbott

Assistant City Attorney