Legislation #: 930961 Introduction Date: 8/19/1993
Type: Ordinance Effective Date: 9/5/1993
Sponsor: None
Title: Approving a $154,400.00 contract with Foley Company for construction of steam lines, Phase V, at the Water Treatment Plant; and authorizing expenditure of $185,000.00 in funding therefor.

Legislation History
DateMinutesDescription
8/19/1993

Prepare to Introduce

8/19/1993

Referred Operations And Aviation

8/25/1993

Advance and Do Pass

8/26/1993

Passed


View Attachments
FileTypeSizeDescription
No attachment(s) found

Printer Friendly Version

 

ORDINANCE NO. 930961

 

Approving a $154,400.00 contract with Foley Company for construction of steam lines, Phase V, at the Water Treatment Plant; and authorizing expenditure of $185,000.00 in funding therefor.

 

BE IT ORDAINED BY THE COUNCIL OF KANSAS CITY:

 

Section 1. That a $154,400.00 contract between the City of Kansas City, Missouri, through its Director of Water and Pollution Control, and Foley Company for construction of steam lines, Phase V, at the Water Treatment Plant is hereby approved and confirmed.

 

Section 2. That the Director of Water and Pollution Control is hereby authorized to expend up to the sum of $185,000.00 from funds previously appropriated to Account No. 801-080-7203-T to satisfy the cost of this contract including changes deemed necessary.

 

_____________________________________________________

 

I hereby certify that there is a balance, otherwise unencumbered, to the credit of the appropriation to which the foregoing expenditure is to be charged, and a cash balance, otherwise unencumbered, in the treasury, to the credit of the fund from which payment is to be made, each sufficient to meet the obligation hereby incurred.

 

 

 

____________________________________

Director of Finance

 

Approved as to form and legality:

 

 

 

___________________________________

Assistant City Attorney